Maryland Line to Five Forks

115 kV Line Rebuild

0

Miles of Line

0 kV

Voltage

Project Need

  • This circuit is among the lowest reliability performers on the BGE transmission systems. Rebuilding this line addresses multiple reliability concerns including; aging infrastructure, aging conductor splices and avian interference

Project Description

  • The scope of the project is to remove the existing two single-circuit 115 kV tower lines (CKT 110901-1 & 110901-2) and replace with a new single-circuit monopole structure line
  • Overall project length is approximately 1.8 miles
  • This project is subject to PSC approval and design changes

Resources

Timeline

Fall 2018

Begin Design and Engineering

Summer 2019

Complete Design and Engineering

Fall 2020

PSC Evidentiary Hearing

December 2021

Project Service Date

Photo Simulation

View looking north from Whiteford Rd. This project is subject to PSC approval and design changes.

Viewpoint Location Map

Web_InsetMap_Maryland-Fiveforks_V2

Construction Sequence

Construction sequence graphics are intended to provide an overview of the typical construction sequence for a project. These graphics are used to give stakeholders a general idea of what to expect regarding this project’s construction process and effort. This project is subject to PSC approval and design changes.

Right of Way Path

Contact BGE

If you have any questions about this project, please contact BGE at BGEProject@BGE.com and refer to the Maryland Line to Five Forks 115 kV Line Rebuild Project. Please include your name and address for prompt follow-up.

  • This field is for validation purposes and should be left unchanged.