Project Description
- Project scope includes reconductoring a double-circuit 230 kV line from Raphael Rd to the Northeast Substation, including replacing existing insulators
- Project includes various modifications at Northeast Substation to accommodate the transmission line rebuild
- Overall project length is approximately 4 miles
- PSC approval received March 4, 2020
- This project is subject to PSC approval and design changes
Resources
Timeline
April 2018
Begin Design and Engineering
February 2020
Complete Design and Engineering
February 2020
Open House Meetings
March 4th, 2020
PSC Administrative Hearing Complete
March 2020
Construction Start
June 2021
Project Service Date

Photo Simulation
View from County Farm Road looking south. The majority of this project is reconductoring the existing double-circuit 230 kV transmission line. Reconductoring is replacing old transmission wire with new transmission wire. This effort will result in minimal visual change. This project is subject to PSC approval and design changes.
Viewpoint Location Map

Construction Sequence
Right of Way Path
Contact BGE
If you have any questions about this project, please contact BGE at conastonewhitemarsh@bge-tsrep.com and refer to the Conastone to White Marsh (PJM 5E) Projects. Please include your name and address for prompt follow-up.